Tuesday, April 24, 2012

Renovation Day 2 - April 24, 2012

All carpets for the counter area and prep area have been removed today.  The goal is to have the prep area front wall and small side wall next to the office removed tomorrow, so we can lay down the tiles on Thursday.  We had three choices on the color for the tiles: grey, beige, and red.  It was a hard decision because all three looks so nice.  We were thinking of mixing all three in a pattern but it looked too busy.  Then we were going for a checker look with red and beige.  However, the final decision was just beige to keep it bright, clean, and simple.  You could never go wrong with a neutral color.

On the electrical side, half the track lights have been installed.  By end of tomorrow the other half will be finished and a sub-panel will be placed into the small glass study room.  At this pace, I think electrical will be completed in a couple days.

Our little contractor is hard at work :)

Renovation Day 1 - April 23, 2012







Blush's renovation begin today! We covered the windows and all glasses on the doors with papers. We used spray paint to write our "coming soon" sign as a fun quick project.







As simple as it looks, it took us a few tries before we can get a decent nice sign.  Spray painting is not as easy as you think.  But it was still fun and quick to have a plain, direct and down to earth sign to let customers know that we will be opening soon.